LNG Upstream Infrastructure Project, Papua New Guinea

LNG Upstream Infrastructure Project, Papua New Guinea
LNG Upstream Infrastructure Project, Papua New Guinea
LNG Upstream Infrastructure Project, Papua New Guinea
  • Oil and Gas, Infrastructure
  • Bridging, Engineering and Project Services
  • Papua New Guinea

Contact us

Jamie Clifton

Commercial Manager

+44 (0)1291 623801

Challenge

The PNG LNG Upstream Infrastructure Project in Papua New Guinea is a major undertaking in which an extensive pipe work system is being installed capable of carrying 6.6 million tonnes per annum of liquid natural gas from its source in the Southern Highlands to the capital Port Moresby.

An undertaking of this scale requires major supporting infrastructure work. This includes the installation of several bridges along the supply route, replacing many local structures that were in a critical need of repair. Amongst the bridges and infrastructure works needed to support the project was a requirement for a bridge spanning 120m across the Kikori River, the upgrading of the existing Highlands Highway and the installation of other bridges to provide access to the site of the Hides Gas Conditioning Plant.

Mabey Bridge was tasked with the fabrication and supply of five bridges to be used in the early phases of the project.

Back to top

Solution

Due to their long spanning capabilities and heavy-duty nature, Mabey Universal bridges were chosen for four of the longer structures (52m, 61m, 63m and 120m). In addition, a Compact 200 was used or the fifth bridge due to the smaller spanning requirement of just 33m.

The first installation was the 61m Mabey Universal Bridge crossing the River Lai. Components were delivered for assembly on the banks of the river. The skeleton structure was pushed over the river, jacked down onto bearings and decking installed. A team of 20 local workers, assisted by a Mabey Bridge Site Advisor, assembled the bridge with the help of a crane. The bridge took only three weeks to build and was successfully launched in April 2010.

Work then began to erect the other bridges, including the most impressive of the scheme – the Kikori River Bridge; a three span, 120m long structure with a double storey centre span. The local labour force, now with valuable bridge erection experience, assembled and launched the bridge over newly constructed piers during an eight-week period.

The remaining bridges were erected independently by the contractor with minimum technical assistance required. As the region experiences many earthquakes, all bridges included seismic restraints.

Back to top

Result

All five structures were installed before the end of 2010. Their installation has allowed the four-year US$15.7 billion project to gain pace, with the scheme on course for completion in 2014. LNG deliveries are scheduled to commence in 2014 and the project will have an expected operational life of 30 years.